The factory has 20 slabs ready and the receiving warehouse in Ukraine has booked an unloading slot. The purchase order gives the product code, thickness and area in square metres. Two practical questions are still open. Which side of the trailer should the driver open? Can the receiver’s forklift lift the entire rack off the vehicle?

An A-frame, often called a cavalletto by an Italian supplier, supports slabs on edge against sloping uprights. For road freight from Italy to Ukraine, the unit the warehouse will receive includes the rack, slabs, edge protection and restraints. Its overall dimensions and gross weight determine whether the collection and delivery arrangements will work.

From slab dimensions to packed weight

Laminam’s technical guide gives a useful example for its 12+ Full Size range. A full standard A-frame takes 20 slabs of nominal size 1,620 × 3,240 mm. The packed unit measures 3,280 × 760 × 1,970 mm and weighs 3,280 kg. A receiving warehouse with a three-tonne forklift already knows it needs different equipment. For an actual order, ask the factory to confirm the figures for each unit it will despatch, particularly for a partly filled rack.

Ask the factory for
What the answer lets you check
Packing list and a photograph of each rack label
Match the order, product code, thickness and slab count. Check the batch or shade code where the finish has to match. The team then knows what to look for as the pack is opened.
Overall length, width, height and gross weight of each loaded rack
Allocate space on the trailer and check the warehouse entrance, forklift manoeuvring space and the area where the rack will stand.
A photograph of the base and the approved fork entry diagram
Establish the approach side and fork length, then check whether the receiving warehouse can lift the rack the same way the factory loads it.

A purchasing team can use the following wording in Italian. “Per il ritiro, potete confermare dimensioni esterne, peso lordo e numero di lastre per ogni cavalletto? Potete inviare una foto della base e lo schema di presa con le forche?” It asks for the overall dimensions, gross weight and slab count per rack, plus a photo of the base and the fork entry diagram.

Match the vehicle to the unloading site before collection

Start at the receiving end. A curtainsider may offer side access while the warehouse takes deliveries only through rear dock doors. If the factory’s diagram calls for the forklift to approach the long side of the rack, arrange access from the yard or agree another unloading site before the vehicle sets off. When booking curtainsider transport, check the clear side opening, the position of the trailer pillars and the space the forklift needs to approach.

Give the handling diagram to the operator. They need the gross weight, approach direction, fork length and load centre distance. They can then check the capacity chart for the forklift and its fitted attachment. For example, Laminam specifies a forklift rated at least 5 tonnes and forks at least 1,200 mm long for a transverse lift of the rack in the range described above. A 3.5-tonne rating would still be insufficient for that lift, even though the loaded rack weighs 3.28 tonnes.

Check every planned transfer. For groupage from Italy, find out which depots will lift the rack off the vehicle and whether each has suitable equipment. If the route involves freight consolidation, agree how the rack and neighbouring loads will be positioned. The forks need a clear approach, and adjacent freight must remain clear of the slab faces and edges in transit. If a hub cannot handle the unit, discuss a direct collection from the factory.

What to record when the haulier takes over

Before collection, give the driver the despatch warehouse address, collection slot and order reference. At the factory, match the rack label to the packing list. For example, a FLORIM stone pack carries an external label identifying the customer and the material on that rack. Check that the order brought to the vehicle is yours, then inspect the visible corners, base, protective pads and restraints. Take an overall photograph, a readable image of the label and close-ups of the accessible edges and any visible damage. For a wrapped pack, record how many labelled units changed hands and which parts could be inspected from the outside.

There are two securing arrangements to check. The factory restraints hold the slabs on the rack. The haulier also secures the rack to the vehicle’s designated anchorage points according to the agreed loading plan. If a support is bent or a retaining band has worked loose, pause the handover, ask the factory to put it right and record the condition before departure.

How to receive the A-frame and record damage

While the rack is on the vehicle. From a safe position, check the rack ID, accessible edges, corner protectors, base and position of the pack. If the frame is leaning or the slabs have shifted, stop unloading. The person supervising the lift must establish how to stabilise it. Keep everyone outside the area into which a slab could fall.

Once the rack is on the ground. Trained staff place it on firm, level ground in the agreed position. Leave the factory restraints in place until the rack is stable and the equipment for handling individual slabs is ready. The operator follows the manufacturer’s unloading sequence, keeps the rack balanced and secures the slabs remaining on it. As the pack is opened, the receiver checks the count, product identification, exposed edges and finish.

If a chip is visible at delivery. Ask the driver to inspect it with you. Photograph the label and the damage with an object for scale, and enter a specific reservation on the CMR consignment note. A reservation could read as follows. “Rack A-02, outer slab, lower right corner chipped over approx. 4 cm. Observed before unloading. Inner slabs covered by packaging.” This records both the condition and when it was observed. Our guide to completing the CMR consignment note covers the rest of the document.

If a crack is found inside the pack. Keep the rack label, packaging and unpacking photographs, and identify the affected slab. For international road carriage under CMR, notify the carrier in writing of concealed damage within seven days of delivery. The delivery day, Sundays and public holidays are excluded from the calculation. Send the notice as soon as the damage is found and retain evidence of sending it.

Who takes back the empty rack?

When the order is confirmed, ask who owns the rack, whether a deposit is charged, who pays for its return and what document the supplier accepts as proof. If it is returnable, photograph its ID and note the return address and deadline before signing off the delivery. Purchasing will still have the details when the last slab goes into production and the empty rack is ready for collection.

Previous article

Latest news

One lorry, several declarations. How to prepare a GMR before leaving Great Britain
Transport and logistics
One lorry, several declarations. How to prepare a GMR before leaving Great Britain
How to collect large-format porcelain slabs in Italy and receive them on an A-frame
Transport and logistics
How to collect large-format porcelain slabs in Italy and receive them on an A-frame
How UN numbers, CAS numbers and customs codes differ for chemicals
Transport and logistics
How UN numbers, CAS numbers and customs codes differ for chemicals
How to read a UN IBC marking and check a container for dangerous goods
Transport and logistics
How to read a UN IBC marking and check a container for dangerous goods
When does a foreign importer need a fiscal representative in the EU?
Transport and logistics
When does a foreign importer need a fiscal representative in the EU?
AEO Status in Ukraine and Its Benefits for International Trade
Transport and logistics
AEO Status in Ukraine and Its Benefits for International Trade