Heavy equipment lift planning: what the crane company and haulier need to know

A “100-tonne crane” cannot lift 100 tonnes at every position on a site. Its capability depends on the actual configuration, radius, height, lifting accessories and set-up conditions. For a customer, the implication is straightforward: machine weight alone is not enough to book the crane.
When arranging machinery or production-line transport, the crane company and haulier need a coordinated set of information. Otherwise they may each prepare a solution that cannot be implemented alongside the other. A lift plan brings the interfaces together: where the load starts, how it moves and where it must be placed.
Customer information and specialist planning are different responsibilities
The customer arranges reliable information from the manufacturer, equipment owner and site owner. Planning is undertaken by a competent person with experience appropriate to the operation’s complexity. The documentation, approvals and allocation of responsibilities depend on the work, contractual arrangements and applicable requirements.
A cargo photograph and an assurance that “the yard is strong” are insufficient. However, the customer is not expected to select slings or calculate crane support loads. Their role is to supply verified information and agree clear work boundaries. For industrial equipment delivery, this is part of confirming loading and receipt before dispatching the vehicle.
Information pack for the lift planner
Information | Required detail | Typical source |
|---|---|---|
Lifting mass | Actual equipment mass in the proposed condition, including frames and items lifted with it | Manufacturer or cargo owner |
Geometry | Drawing showing dimensions, protrusions, transport orientation and reference datum | Manufacturer or owner’s technical specialist |
Centre of gravity | Coordinates confirmed for the actual configuration | Manufacturer or authorised engineer |
Lifting points | Locations, rated loads, permitted force directions and manufacturer restrictions | Manufacturer or structural designer |
Site | Layout, levels, buried services, surface and ground-bearing information | Site owner with relevant specialists |
Transport | Vehicle position, deck height, support zones and required cargo placement | Haulier |
Organisation | Work window, access, exclusion arrangements, responsible people and nearby activities | Customer and contractors |
The crane contractor separately accounts for slings, spreaders and other lifting accessories, together with the deductions required by the particular crane’s load-chart instructions. The machine’s weight alone is not the complete load assessment.
The nameplate weight may describe a different configuration. Removing a component, adding a frame or changing fluid contents can affect both mass and centre of gravity. Preparing the machine is covered in our equipment transport preparation guide; the crane information pack should contain the confirmed outcome of that preparation.
Why the drawing must show the centre of gravity and lifting points
The centre of gravity affects the load’s behaviour as it leaves its supports and the distribution of forces. A visually symmetrical enclosure does not establish symmetrical weight distribution. A heavy drive or cabinet may sit on one side.
The drawing must identify more than the lifting lugs: it should state permitted loading directions and manufacturer restrictions. Transport securing points must not automatically be treated as lifting points. The lift designer determines the need for a spreader, sling lengths and permitted geometry for the particular load.
For energy-sector equipment logistics, record which attachments remain on the unit. A plan approved for the main body without accessories cannot automatically be applied to another configuration.
Site space must accommodate the crane as well as the truck
Show the crane position, support footprint, vehicle position, initial and final load locations, obstructions and movement path. Operating radius is measured from the crane’s centre of rotation to the vertical load line; bumper-to-machine distance is not that measurement.
Check access for arrival and assembly, plus delivery of counterweights and lifting accessories where needed. A gateway may admit the low-loader while the yard lacks room to deploy outriggers or operate the boom. Photographs supplement measured information; they do not replace it.
Asphalt or concrete alone does not establish ground suitability
The site owner needs to identify drains, ducts, basements, tanks and other voids beneath the proposed set-up area. An unbroken surface does not reveal what is below it. The crane contractor supplies the support reactions or crawler loads needed for assessment in the selected configuration; appropriate specialists establish site suitability.
Simply dividing the combined crane and load weight between four outriggers is not sufficient: reactions vary with boom and load position. Mat or spreader-pad size should not be guessed either. The practical customer question is: who confirms the support conditions, using which information?
Ports may impose separate access, equipment-positioning and work requirements. Agree them through the port forwarding arrangements before booking the shift, rather than after the crane team arrives.
Coordinate the crane operation with the low-loader
The haulier supplies deck characteristics, support locations and the required load position relative to the axles. The crane contractor checks that the equipment can be placed there. For low-loader transport, access to securing points and removal of lifting accessories after landing are also important.
If the machine must move again once on the deck, plan that as a separate operation. It should not be improvised after lifting. Restraint for transport and rigging for lifting serve different purposes and do not replace one another.
Example: unchanged weight, revised plan
An illustrative 18-tonne unit is to be lifted from a trailer beside a workshop entrance. A site inspection identifies an underground duct beneath a proposed outrigger position. Moving the crane and truck would change the operating radius and load path.
The immediate conclusion is not simply “order a slightly larger crane”. Specialists first review the layout, ground conditions, configuration, load chart and work area. Equipment is confirmed after that assessment. The example shows why unchanged cargo weight does not validate the original plan.
If changing the trailer also changes the loaded height or cargo position, reassess the oversized transport arrangements. The approved lift and road movement must concern the same configuration.
What should be settled before work starts
The agreed plan or document pack should identify the cargo, crane configuration, lifting accessories, layout, sequence, responsible people and communication method. Define stop conditions as well: changed load data, unsafe weather, unauthorised people entering the area, loss of communication or another identified event.
Wind limits depend on the equipment, configuration and load characteristics, including exposed area. A single wind-speed limit is unsuitable for every lift. A tandem lift with two cranes is also not a simple addition of their rated capacities; it needs specific planning.
Agree the handover point: who confirms the load is on its supports, when the lifting operation ends and when the equipment is ready for transport securing or installation. Our equipment transport control guide addresses the broader journey; this article focuses on the crane–load–vehicle interface.
The enquiry that starts a useful assessment
Send drawings and photographs, confirmed weight, centre-of-gravity information, lifting-point details, both site layouts, addresses and preferred dates. Identify missing data explicitly. An unknown parameter needs obtaining or verification, not a convenient assumption.
Save Pro Solutions coordinates the transport scope and contractor interfaces within industrial project logistics. We will identify the information still required, align vehicle positioning with lifting operations and prepare a proposal with a clear scope. The specific lift plan remains the responsibility of the competent parties appointed to develop and approve it.